Behind the Win: Bringing new life to the Downing Centre
Winner: Restoration/Adaptive Re-Use of an Historic Building ($10M–$20M), 2026 Master Builders Excellence in Construction Awards
When a burst water main forced the Downing Centre to close in June 2025, the immediate priority was getting NSW’s busiest courthouse back into use. For the Department of Communities and Justice (DCJ), the closure also offered a rare opportunity to improve public areas and support spaces while the building was offline.
Engaged by BGIS and DCJ, we delivered a three-month refurbishment across seven levels. The project has since won the Restoration/Adaptive Re-Use of an Historic Building ($10M–$20M) category at the 2026 Master Builders Excellence in Construction Awards.
Behind that recognition was a team working through an evolving brief, incomplete building records and a two-week shutdown of the building’s power.
Making decisions where the work was happening
With limited design completed at engagement and no traditional pre-construction phase, we mobilised immediately. Design and construction had to progress together.
Working closely with Architectus, with a full-time architect on site, we resolved details through site walks and workshops. Joinery workshops helped streamline approvals, while clear change management kept DCJ, the consultants and our team aligned as the work developed.
Procurement needed the same close attention. Where specified items could not meet the program, we worked with the design team to identify alternatives that retained the design intent.
Planning for two weeks without lifts or power
The planned building-wide power shutdown would remove access to lifts, lighting and normal power supplies while construction was underway.
Before it began, we moved materials and equipment onto the floors where they would be needed wherever possible. Temporary flood lighting supported work areas, a generator supplied critical functions, and we relocated the site office to maintain operations.
Access required its own solution. With the loading dock unavailable, we constructed a temporary ramp to move materials into the building while protecting the heritage steps. Deliveries were coordinated through supervised sheriff access.
Improving the experience of coming to court
The refurbishment focused on making public spaces more welcoming and practical for the people using them.
Reducing existing ceiling bulkheads opened up spaces and improved access to natural light. Upgraded meeting and interview rooms incorporated acoustic panelling to support privacy. Refreshed parents’ and first aid rooms, improved amenities and dedicated male and female multi-faith rooms better accommodated court users’ needs.
Respecting the building’s heritage also meant looking carefully at what could stay. Existing courtroom joinery was repolished, furniture was salvaged for use elsewhere, and timber shrouds refreshed existing glazed aluminium partitions without unnecessary demolition. The project diverted 95.7% of waste from landfill.
The award recognises a refurbishment delivered under considerable pressure. For us, the lasting achievement is the contribution these spaces make to a more welcoming and accessible courthouse, with its heritage character retained.
Delivered with DCJ, BGIS, Architectus, FPOV and Genus Advisory.