Building around the working week at Chifley Tower. Refurbishing three floors while a tenant stayed in place.

Chifley North Tower | Multi-Level Refurbishment

We refurbished 6,000sqm across three floors of Chifley Tower for Charter Hall, preparing spaces for future leasing. 

On Level 10, the shared lobby had a deadline every week: Monday morning. An existing tenant was staying throughout the build, so the entrance needed to be usable and presentable after each weekend of construction. 

Our team rebuilt the lobby in stages, installing temporary floor and wall finishes between them. Levelled carpet and temporary lighting kept the entrance working during the week, even as the permanent finishes took shape around it. 

That occupied lobby was one part of a project where each floor needed a different approach. Working with Calibre Project Management and designer alkimi, we stripped Level 11 back to a cold shell and divided Level 13 into two tenancies. Level 10 combined cold-shell areas with a new speculative suite. 

Reused workstations were incorporated into the Level 10 suite, keeping existing furniture in service. 

Getting materials upstairs 

The constraints extended beyond the spaces being refurbished. A small loading dock served multiple builders while construction continued across the precinct, and two other builders were working on the same floor. 

Our team coordinated shared access with building management and the other contractors. With the goods lift out of service, we used a passenger lift to bring materials to the work floors. 

Behind the floating ceilings 

The finished lobbies bring together Italian stone and raked plaster, with symmetrical joints running through the stone floor tiles. Above, illuminated ceilings appear to float overhead. 

That effect began with the framework. Intricate framing formed coffers and recesses within the ceiling, creating the suspended appearance of the illuminated surface. 

Stone vanities and dry benches feature in the refurbished bathrooms. Within the Level 10 suite, feature ceilings mark the entry and boardroom, including a felt finish in the boardroom. 

We completed the refurbishment in June 2026, with the Level 10 tenant operating throughout construction. 

  • Location

    2 Chifley Square, Sydney

  • Size

    6,000 sqm (over three floors)

  • Partners

    Calibre Project Management, alkimi, GWA Consultants, ER&D and Nutbrook Group, WT Partnership

  • Delivery Method

    Design and Construct