A workplace built to connect people 

Winner: Interior Fitouts ($15M–$17M), 2026 Master Builders Association of NSW Excellence in Construction Awards 

At Parkline Place, connecting teams started with opening up the floors between them. 

Property and Development NSW (PDNSW) wanted a workplace that would bring agencies together and support different ways of working. The Department of Planning, Housing and Infrastructure and the Department of Climate Change, Energy, the Environment and Water would share a 4,450sqm home across Levels 10–12. Making those floors work as one connected workplace required careful decisions about the structure and the details people would encounter every day. 

Opening up the floors 

Cutting through post-tensioned concrete slabs for the new stairs had to be carefully managed to protect the building’s structural integrity. We used detailed investigation and engineering validation to establish the sequence and controlled cutting methods before work began. 

Around those openings, six trades had to bring their work into alignment. The curved lighting needed to follow the ceiling precisely, alongside the fire curtain, staircase and adjoining finishes. Through workshops with consultants and specialist trades, we layered shop drawings to resolve how the elements would fit together. Templates based on the stair opening established the shapes for the ceiling and lighting. 

Resolving those relationships before installation helped preserve the clean, continuous lines of Davenport Campbell’s design. The finished detail gives little away about the coordination behind it. 

Getting the glass right 

Davenport Campbell developed the design concept of “converge and intertwine” with First Nations consultant Yarnnup. The blue gradient in the stair balustrades, inspired by Australia’s waterways, carries that idea through the centre of the workplace. 

Reproducing it in glass took repeated testing. Light behaved differently through the straight and curved sections, changing the appearance of the printed gradient. A colour that worked in one section did not necessarily look the same in the next. 

We worked through successive prototypes with the design and specialist teams, adjusting the gradient until the sections appeared consistent. The process also allowed the team to test performance and refine the details before installation. It protected a distinctive part of the design while giving us greater certainty about how it could be built. 

Making flexibility work

The same attention was needed in the spaces around the stairs. Operable walls allow smaller meeting spaces to open up for town hall gatherings. With long lead times on both the walls and fire curtains, we placed orders early and coordinated installation with neighbouring trades to protect the program. 

Material choices needed practical testing too. Cork brought warmth and acoustic benefits to gathering spaces, but installing it around curved walls required care. We trialled a section and worked through installation options with the architect before agreeing the approach for the remaining work. 

These decisions helped realise a workplace with more choice built into the day. 

Sustainability in practice 

During construction, we diverted 96% of waste from landfill. First Nations businesses accounted for 11.56% of project spend and a ESG reporting helped maintain visibility of workforce participation throughout delivery.

Adapting as the building became occupied 

As construction progressed, the tower began welcoming occupants. We adjusted staging and access arrangements, moving stair cut-outs and other noisy activities outside peak occupancy periods. Working closely with Investa helped us coordinate loading dock access and deliveries, while collaboration with the base builder helped resolve defects and services interfaces as they emerged. 

We also planned backwards from the agencies’ move. Communications rooms were handed over four weeks before practical completion, giving the tenant teams time for commissioning and preparation. During the final week of construction, staged access allowed tenants to begin moving in while we completed the remaining works. 

Working with PDNSW, Sandstone Project Management, Davenport Campbell, DBS Consulting and the wider consultant and trade teams, we completed the workplace on its planned date. We’re proud to see that shared effort recognised with a Master Builders award.